Home/Case study/Madre Giuseppina Vannini Hospital, Rome
Healthcare · Rome

Madre Giuseppina Vannini Hospital, Rome

IFM renewed the boiler room, chiller plant and part of the substation at Madre Giuseppina Vannini Hospital, while the hospital remained fully operational.

Client Istituto Figlie di San Camillo
Project at a glance
Client
Istituto Figlie di San Camillo
Location
Madre Giuseppina Vannini Hospital, Rome
Period
2022 – 2024
Plant
Approx. 2,100 kW heating and 500 kW cooling

At Madre Giuseppina Vannini Hospital in Rome, IFM renewed the heating and cooling plant serving the hospital and its management offices: three new boilers totalling about 2,100 kW and two chillers totalling about 500 kW, with the hospital in use throughout.

The client

The Istituto Figlie di San Camillo is a religious institute running hospitals and care facilities dedicated to patient care and specialist services. Madre Giuseppina Vannini Hospital, set within the urban fabric of Rome, houses wards, outpatient clinics, diagnostic areas and clinical support spaces.

Its building services must be reliable, safe and continuous, and provide comfortable conditions for patients and staff.

The challenge

The task was to work on essential plant in a live hospital, without interrupting care and with minimal disruption to wards, clinics and diagnostic areas.

Suitable indoor conditions had to be maintained throughout, and the plant room renewal had to be coordinated with the internal energy distribution network.

The solution

The works were planned in phases, coordinating the plant room renewal with the upgrade of the substation. The project included:

  • a rebuilt boiler room with three new boilers, totalling about 2,100 kW;
  • a new chiller plant with two chillers, totalling about 500 kW;
  • the rebuild of part of the plant substation and the internal energy distribution network serving the hospital buildings.

The new equipment has improved plant reliability and energy efficiency, while essential services were kept running for the full duration of the works.

Technology

Latest-generation boilers for heat production and chillers for cooling. The plant substation and the relevant section of the distribution network were upgraded to match the new generation systems.

Why it stands out

The project was delivered entirely within a hospital that stayed operational at every stage. Combining the renewal of the heating and cooling plant with the upgrade of internal distribution made it possible to treat the whole affected energy system as one, with a clear focus on continuity of service, safety and plant reliability.