I.F.M. maintains the buildings and building services of the INAIL – A.S.P. Catanzaro Integrated Centre, keeping its healthcare, care and research activities safe and running without interruption.

Client INAIL – A.S.P. Catanzaro Integrated Centre
Project at a glance
Client
INAIL – A.S.P. Catanzaro Integrated Centre
Location
Lamezia Terme (Calabria)
Period
2025 – 2029
Portfolio
2 buildings, approx. 12,000 m² gross

At the INAIL – A.S.P. Catanzaro Integrated Centre in Lamezia Terme, I.F.M. manages the building services of a healthcare and research facility that never stops. A programme of repairs and upgrades has made the systems safer and more reliable, and reduced the frequency of failures.

The client

The INAIL – A.S.P. Catanzaro Integrated Centre is a strategically important complex for the area, housing care, diagnostic, outpatient, administrative and scientific activities. The portfolio comprises two buildings on the same site, with a combined gross floor area of around 12,000 m².

Having healthcare and research under one roof demands a high level of reliability and operational continuity. Key assets include solar thermal systems, chillers, air handling units, UPS systems, dust extraction plants and compressed air generation and distribution.

The challenge

At the start of the contract, building and services alterations had to be carried out in a fully operational facility, to add intensive and high-dependency care beds and to expand the emergency department. The work called for close coordination of complex civil and building services works, tight deadlines and compliance with the safety and hygiene standards of a clinical environment, while keeping disruption to active wards to a minimum.

The initial technical assessment also identified the need for corrective work across several systems, starting with Legionella risk management in the water networks.

The solution

Building on the initial surveys, I.F.M. launched a programme of corrective maintenance, refurbishment and improvement:

  • Water systems: extraordinary Legionella remediation and a permanent continuous-dosing treatment and control system; cleaning, sanitisation and optimisation of domestic hot water production, and recommissioning of the solar thermal system.
  • Lifts: replacement of obsolete components, resolution of issues raised in periodic inspections, and upgraded communication and safety systems.
  • Electrical systems: redundant solutions for continuity of supply and refurbishment of infrastructure and lighting, improving safety and efficiency and reducing consumption.
  • Fire protection: active and passive protection systems restored to full working order and detection devices brought up to standard.
  • HVAC and special systems: major maintenance on the main equipment and recommissioning of the extraction and compressed air systems.

Technology

The contract is run on the ISI FM information system, which handles maintenance planning and traceability, a digital asset register of buildings and systems, ticket management and reporting. The SAUTER supervision and remote management platform allows the main systems to be monitored and controlled remotely. Integrating the two speeds up operational decisions and provides continuous performance monitoring.

Why it stands out

The project shows how complex building services issues can be tackled systematically without interrupting a working healthcare facility. On biological risk, fixing the immediate problems was backed by permanent control systems and procedures. Coordinated management of every system, based on monitoring, planned maintenance and technical upgrades, prevents failures and reduces the risk of service disruption, protecting patients, staff and visitors.

A single point of contact for buildings and infrastructure