Home/Case study/ASL Rieti, San Camillo de Lellis Hospital
Healthcare · Rieti

ASL Rieti, San Camillo de Lellis Hospital

IFM upgraded the critical care areas of San Camillo de Lellis Hospital in Rieti: intensive care, a new high-dependency unit and an expanded A&E department.

Client ASL Rieti (Rieti Local Health Authority)
Project at a glance
Client
ASL Rieti (Rieti Local Health Authority)
Location
San Camillo de Lellis Hospital, Rieti
Period
2022 – 2025
Portfolio
Hospital with approx. 440 beds

At San Camillo de Lellis Hospital in Rieti, IFM carried out the building and services works to expand intensive care, high-dependency care and A&E, as part of the hospital network reorganisation set out in Decree-Law 34/2020. The most disruptive works were done at night so the hospital never had to stop.

The client

ASL Rieti runs San Camillo de Lellis, the main public hospital in the province and the reference centre for the whole Rieti area and beyond. It has around 440 beds across general wards, day hospital, intensive and high-dependency care, long-term care and rehabilitation, and plays a key role in emergency care.

In a high-acuity hospital, continuity of building services and availability of clinical spaces are essential to patient safety.

The challenge

The site had to coexist with live wards and high-acuity areas. That meant managing access, the movement of materials and workers, noise and dust, while coordinating with patient and staff routes.

Works on the services supplying clinical areas also carried a risk of interrupting essential services, with tight deadlines and very little room for taking spaces out of use.

The solution

The contract increased intensive care capacity by refurbishing part of the intensive care unit, created 12 high-dependency beds and expanded A&E with new observation areas for patients with suspected COVID-19, separating patient flows. To deliver this, IFM used:

  • phased planning, with the most disruptive works carried out mainly at night;
  • services works coordinated with clinical needs and space availability;
  • low-noise machinery, mobile acoustic barriers and dedicated scheduling of noisy tasks;
  • reconfiguration of internal spaces, including demolition, new layouts, new windows and doors, and finishes;
  • new toilet facilities with water supply and drainage networks;
  • new air conditioning, air handling and medical gas distribution systems;
  • completion and upgrading of electrical and specialist systems.

Technology

Construction choices comply with Italy’s Minimum Environmental Criteria (CAM) under the Ministerial Decree of 11 October 2017. Thermal and acoustic insulation with recycled content was used for partitions and finishes.

Indoor and outdoor lighting uses latest-generation LED luminaires, offering high efficiency, long service life and low maintenance costs, improving visual comfort and reducing energy use.

Why it stands out

The project combined building refurbishment, services upgrades and expanded critical care capacity in a hospital that stayed open throughout, keeping disruption to wards and clinical routes to a minimum.

The hospital now has greater capacity to respond, with new intensive and high-dependency beds and a larger A&E. The approach can be replicated in other complex projects in working healthcare facilities.